FAQ

Frequently Asked Questions

General Questions

  • Obtain application form UL9 from revenue clerk
  • Complete form and attach copies of National ID and Proof of Capital
  • Forms are submitted to the revenue clerk and sent to the Land Management Committee.
  • Land Management Committee reviews applications and makes recommendations to the CEO
  • CEO app roves/ reviews recommendations
  • Planning Department issues offer letters and conditions of establishment.
  • You pay a deposit fee
  • You pay instalments.
  • You produce building plans.
  • Plans are approved
  • Lease agreement signed.
  • You begin construction.
  • Roads and works Department conducts building inspections
  • Obtain application form UL 2 or CL E1 from revenue clerk
  • Complete form and attach copies of National ID, and Lease Agreement.
  • Forms are submitted to the revenue clerk and sent to the Land Management Committee.
  • Land Management Committee reviews applications and makes recommendations to the CEO
  • CEO approves/ reviews recommendations
  • Extension/alteration addendum affixed to original lease agreement
  • Revenue updates database.
  • Obtain application form TPD1 from revenue clerk
  • Complete form and attach copies of Title Deeds, Site Development Plan, Preliminary Working Drawings and Narrative Proposal/report
  • Forms are submitted to the revenue clerk and sent to the Planning Department
  • Planning Drafts statutory advert and sends it to the Herald at your cost. (30 Days)
  • Objections/representations are received
  • Land Management Committee reviews applications and makes recommendations to the CEO
  • CEO approves/ reviews recommendations
  • CEO issues/denies Development Permit
  • Final working drawings produced and approved.
  • Building permit issued
  • You begin construction.
  • Roads and works conducts building inspections.

 

  • Obtain application form S.L. 3 from revenue clerk
  • Complete form and attach copies of National ID, approved plans and health inspector’s report.
  • Forms are submitted to the revenue clerk and sent to the Land Management Committee
  • Land Management Committee reviews applications and makes recommendations to the CEO
  • CEO approves/ reviews recommendations
  • You pay licence fees
  • Revenue clerk issues new licence.
  • You affix licence on premises and begins trading.
  • You pay licence fees
  • Revenue clerk issues new licence.
  • You affix licence on premises and begins trading.
  • Submit Plans to the Planning Department
  • Planning Department computes and endorses total architectural area at the back of one copy
  • The Revenue clerk computes examination fees and records plan at the back of the same
  • You pay Plan approval fees
  • The Revenue clerk records plan and sends it to the Plan Examination Committee
  • Plan Examination Committee approves or reviews plans and sends them back to revenue clerk
  • Building permit issued
  • You are invited to collect your approved plans
  • You begin construction.
  • Roads and works Department conducts building inspections.